针对我国目前大容量机组的投产和小容量机组的关停,漳泽发电厂由原来的基荷电厂改为调峰电厂。为适应网间潮流要求,机组运行工况发生了很大变化,产生了许多问题。着重对苏制215MW燃煤机组在网间潮流调峰过程中如何选择最佳调峰方式,使变负荷调峰的参数达到优化、运行方式进行了较深入的分析,结合电网情况,确定了最佳调峰运行方式,对机组出现的若干问题给出了有建设性的结论。
Due to the production of the mass capacity motor and the breakdown and suspend of the less capacity motor at present in China,Zhangze Power Plant has changed over from basic power plant to adjustpeak power plant.In order to adapt the demand for the prevalence of network,the great change has been taken place for the motor function,which caused lots of problems.Combined with electrical network,the article focused on deep analysis about how to choose the best way of adjustpeak in the process of network prevalence adjustpeak,which can optimize the parameter of capacity turned adjustpeak.The article not only confirms the best way of adjustpeak function,but gives the constructive conclusion of those problems caused by unit.
出处
《山西电力》
2003年第A01期17-19,38,共4页
Shanxi Electric Power
关键词
苏制215MW机组
调峰运行
汽轮发电机组
变负荷速率
tidal current between network
adjust-peak method
parameter of changing-load adjust peak
speed of changing load