不同合龙方式对多跨刚构-连续梁组合体系梁桥施工监控的影响分析 被引量:1

The Influence Analysis of Different Closure Ways on Construction Monitoring of Multi-span Rigid-frame Continuous Beam Composite System Beam Bridge
下载PDF
导出
摘要 长联多跨刚构-连续梁组合体系桥梁结构及受力复杂,不同合龙顺序对施工过程中结构成桥累计位移和内力影响很大,以一联(82.68+4×152+82.8)m刚构-连续梁组合体系桥梁为例,采用有限元法计算分析4种不同的合龙方式对施工阶段主梁位移及内力的影响,并分析合龙口两端产生位移差值的原因,施工中可通过分批、分阶段施加预应力来降低位移差值,以减小施工监控的难度。并综合从桥梁施工监控线形、应力以及工期等方面考虑,指出本类型桥梁合理的施工顺序。 Taking a multi-span rigid-frame continuous beam composite system bridge as an example, using the finite element calculating method, this paper analyzed the influence of four different ways of closure on the main beam displacement and internal force in the construction stage.It also analyzed the reasons of the displacement difference at both ends of the final closure.Comprehensively from the bridge construction monitoring linear, stress and time limit, it pointed out the reasonable construction sequence of this type of bridge.
作者 杜光
出处 《山西交通科技》 2016年第6期70-73,共4页 Shanxi Science & Technology of Transportation
关键词 刚构-连续梁 合龙顺序 施工监控 有限元 rigid-frame continuous beam closure sequence construction monitoring finite element
  • 相关文献

参考文献3

二级参考文献23

共引文献83

同被引文献1

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部