摘要
小浪底引黄工程是山西省内重要的引调水工程之一。文中主要介绍了工程引水干线土洞段的安全监测设计。包括监测断面位置的选择和具体仪器的布置方式,以及后续施工过程中所进行的优化设计与调整。对以后类似工程的监测设计提供了一定的参考。
The Xiaolangdi Yellow River Diversion Project is one of the major water diversion projects in Shanxi Province. The safety monitoring design of earth tunnel section of the water diversion route of this project was introduced.The contents of the design included selection of the monitoring section location,arrangement of the instruments,optimization design and adjustment in the follow-up construction. The design results could provide reference for monitoring designs of similar projects in future.
出处
《山西水利科技》
2016年第3期61-62,66,共3页
Shanxi Hydrotechnics
关键词
小浪底引黄工程
引水干线
土洞
安全监测
the Xiaolangdi Yellow River Diversion Project
water diversion route
earth tunnel
safety monitoring