桃花铺一号隧道TBM施工围岩坍塌和防治 被引量:4

CountryRock Collapse and Prevention of the Taohuapu 1st Tunnelin TBM Construction
下载PDF
导出
摘要 西南线桃花铺一号隧道施工采用全断面隧道掘进机 (TBM ) ,施工过程中多次发生围岩坍塌 ,对施工安全和掘进效率产生了较大影响。结合隧道围岩的工程地质特征 ,分析了坍塌发生的原因、类型和危害程度 ,以及施工中所采取的防治措施 ,对进一步加强。 The Full Face Tunnel Boring Machine(TBM) was adopted in the constructionof the Taohuapu 1st tunnel in the southwest railway line ,the country rock of this runnel have happened many times collapse accidents during the construction ,which made heavy influences on construction safety and boring efficiency, this paper analysed the accidents reasons、type and damage degree of collapse and the prevention measures for it in the construction。In addition,it also made a helpful discussion on further strengthening and improving the construction methods of TBM in order to prevent the collapse of the country rock efficiently。
出处 《西部探矿工程》 CAS 2003年第11期89-90,共2页 West-China Exploration Engineering
关键词 TBM 围岩坍塌 原因分析 防治措施 TBM country rock collapse reason analysis prevention measure
  • 相关文献

参考文献4

  • 1铁道第一勘察设计院.西南线桃花铺一号隧道TBM施工地质超前预报总报告[R].兰州,2002..
  • 2铁道第一勘察设计院.西南线桃花铺一号隧道设计说明[R].兰州,2000..
  • 3北t京.铁路工程地质手册[M].中国铁道出版社,1999..
  • 4昝成忠,熊四华,姚勇,李国礼.软弱围岩条件下的隧道设计与施工探讨[J].工程勘察,2002,30(4):42-44. 被引量:7

二级参考文献1

共引文献6

同被引文献57

引证文献4

二级引证文献123

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部