田湾核电站失去外电源的概率风险评估 被引量:1

Probabilistic Risk Assessment for Loss of Offsite Power of Tianwan Nuclear Power Plant
下载PDF
导出
摘要 对江苏田湾核电站失去外部电源(Loss of offsite power, LOSP)事件进行概率风险评估。考虑了核电站接入华东电力系统后电网与系统间的相互影响,指出导致核电站失去外电源的4个事件:①主网稳定破坏;②计划检修与故障重迭,导致4个回路联络线全部不可用;③飓风导致断线,使4个回路联络线全部不可用;④500kV及220kV主变电站电气设备故障,主变全部停电,使核电站失去外电源。给出这4个事件的计算方法和定量计算结果,并给出了提高可靠性的措施。 This paper proposed a comprehensive probabilistic risk assessment method for evaluation of loss of offsite power events in Tianwan Nuclear Power Plant (TNPP). TNPP is connected to East China Power System (ECPS). TNPP and ECPS are interdependent. There are 4 events which may cause TNPP loss of offsite power are considered in the method: 1. Loss of power system stability; 2. Unavailability of total links between TNPP and ECPS caused by overlapping of scheduled maintenance and forced outages; 3. Un-availability of total links between TNPP and ECPS caused by severe weather; 4. Unavailability of step-up 500kV and 220kV substations caused by equipment failures. Calculation methods and results of these 4 events were provided. Some actions to improve the reliability of system are proposed.
出处 《核动力工程》 EI CAS CSCD 北大核心 2003年第5期478-481,共4页 Nuclear Power Engineering
关键词 概率风险评估 核电站 失去外部电力 可靠性 Probabilistic risk assessment Nuclear power plant Loss of offsite power Reliability
  • 相关文献

参考文献4

  • 1刘肇旭,徐征雄,王德生,印永华,陈企平,潘世华.大亚湾核电站的外部电网运行可靠性评价[J].中国电力,1994,27(11):2-4. 被引量:3
  • 2周孝信.中国电力百科全书:电力系统卷(第二版)[M].北京:中国电力出版社,2000..
  • 3郭永基.工程可靠性原理[M].北京:清华大学出版社,2001..
  • 4周孝信.中国电力百科全书,电力系统卷(第二版)[M].北京:中国电力出版社,2000..

共引文献2

同被引文献6

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部