摘要
深圳沙湾隧道是广东省东江—深圳供水改造工程中开挖断面最大、地质条件最差的隧道 ,施工中结合工程特点和难点 ,在隧道进、出口段采用了超前大管棚和土钉墙联合支护技术。文章就支护的理论分析。
Shawan tunnel in Shenzhen is the one with the largest section and the worst geologic condition in the water-supply renovation works from East River to Shenzhen in Guangdong. Considering the features and difficulties of the project, a combined supporting technology with advance big pipe roofing and earth-nail wall has been adopted at the entrance and exit sections. This paper describes the theoretical analysis, construction technology and quality inspection of the supporting system.
出处
《现代隧道技术》
EI
2003年第5期17-20,共4页
Modern Tunnelling Technology
关键词
土质隧道
支护
管棚
土钉
监测
Tunnel embedded in soil
Support
Pipe roofing
Earth nail
Monitoring