龙滩水电站枢纽布置及重大问题研究 被引量:4

Study on the general layout and key technical issues of Longtan Hydropower Project
下载PDF
导出
摘要 龙滩水电站是红水河上的"龙头"电站,该工程以发电为主,兼顾防洪和航运,具有巨大的综合利用与规模经济效益。其装机容量初期为4900MW,最终为6300MW,枢纽布置从部分坝后厂房加部分地下厂房方案优化为左岸全地下厂房方案,工期提前1年,效益巨大。拦河大坝采用碾压混凝土重力坝,最大坝高初期为192m,最终为216 5m,是目前世界上最高的碾压混凝土重力坝。 The Longtan Hydropower Project is a key project in the cascade development of the Hongshui River. The Project is a multi-purpose hydro scheme with power generation as its primary purpose concurrent with flood control and navigation benefits. The project has an installed capacity of 4900 MW in the first stage with a planned expansion to 6300 MW in the second stage. All underground powerhouse is arranged in the left bank, which makes the construction period to be shortened one year ahead of time. The RCC gravity dam with a height of 192m in the first stage and 216.5m in the second stage will be the highest RCC dam in the world.
作者 冯树荣
出处 《水力发电》 北大核心 2003年第10期37-40,共4页 Water Power
关键词 枢纽布置 碾压混凝土坝 龙滩水电站 general layout, RCC, Longtan Hydropower Project
  • 相关文献

参考文献1

同被引文献12

引证文献4

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部