通过对变压器预试时夹件对地绝缘不良的分析 ,找出了缺陷部位 ,认为要重点加强监视 ,及时发现问题 ,并及时处理。
In this article, through the analysis of poor insulation between clamping piece of transformer and ground, the defect position is found. It is proposed that the defect position has to be monitored after it has been put into operation, the fault has to be found and treated in time.
出处
《高电压技术》
EI
CAS
CSCD
北大核心
2003年第10期56-57,共2页
High Voltage Engineering