摘要
近年来,由于变电站自动化系统在无人值守变电站中的应用越来越广泛,其出厂前验收工作也越来越受电力部门的重视。结合广东省佛山地区近年来对220kV和110kV无人值守变电站自动化系统的验收经验,对出厂前验收时应注意的问题进行了分析,指出了验收工作的关键点,并提供了基本的验收方法。
Along with the widely use of the substations automation systems, the acceptance before delivery is getting more and more attention from the power unit.Based on the experience of 110 kV and 220 kV substations, acceptance before delivery in Foshan region, the problems to which should be paid attention are analyzed. The basic inspecting is also provided.
出处
《湖北电力》
2003年第5期25-26,共2页
Hubei Electric Power