摘要 电力系统可用输电能力 ATC是电力市场形势下衡量系统区域间电能传输能力的重要指标 ,本文着重阐述了在电力系统静态电压稳定下各预想事故对区域间输电能力的影响 ,并初步探讨了此类事故的分析 。 Available Transfer Capability(ATC) is the measure of the ability of interconnect ed power systems to reliably move or transfer power from one area to another.It is an important index in power market.In this paper,transfer capability in conti ngency has been analyzed based on the constraint of voltage stability,and the ra nking of these contingencies has been discussed.
机构地区 浙江大学
出处 《电力系统及其自动化学报》 CSCD 2003年第5期5-8,27,共5页 Proceedings of the CSU-EPSA
关键词 电力系统 电网 电压稳定 最大输电能力分析 可靠性 available transfer capability TTC contingency voltage stability ranking
  • 相关文献

参考文献12

  • 1江伟,王成山.电力系统输电能力研究中PV曲线的求取[J].电力系统自动化,2001,25(2):9-12. 被引量:53
  • 2李国庆,董存.电力市场下区域间输电能力的定义和计算[J].电力系统自动化,2001,25(5):6-9. 被引量:14
  • 3Canizares C A ,Alvarado F L. Point of collapse and continuation methods for large AC/DC systems [J]. IEEE Trans. on Power Systems, 1993,8 (1) : 1- 8.
  • 4Alvarado F L,Dobson I,Hu Y. Computation of closest bifurcation in power systems[J]. IEEE Trans. on Power Systems, 1994,9(2) : 918- 928.
  • 5Iba K, et al. Calculation of critical loading condition with nose curve using homotopy continuation method[J]. IEEE Trans. on Power Systems, 1991,6(2) : 584-593.
  • 6Zeng Z C,Galiana F D,Ooi B T,Yorino N. A simplified approach to estimate maximum loading conditions in the load flow problem[J]. IEEE Trans. on Power Systems, 1993,8 (2): 646- 654.
  • 7Scott Greene, Ian Dobson, Fernando L Alvarado. Contingency ranking for voltage collapse via sensitivities from a single nose curve [J]. IEEE Trans. on power systems, 1999,14 (1) : 232- 240.
  • 8Vaahedi E,Fuchs C,Xu W,Mansour Y,Hamadanizadeh H, Morison G K. Voltage stability contingency screening and ranking[J]. IEEE Trans. on Power Systems, 1999,14 (1): 256- 265.
  • 9Sandrin P, Dubost L, Feltin L. Evaluation of transfer capability between interconnected utilities[A]. Proc. of the 11th Power System Computation Conference[C].Avignon, France, 1993.
  • 10Available Transfer Capability Definitions and Determination:A Reference Document Prepared by TTC Task Force [R]. North American Electric Reliability Counci1,1996.

二级参考文献3

共引文献65

同被引文献76

引证文献8

二级引证文献44

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部