株洲市第四水厂于1996年10月开始建设,1999年12月建成通水,日处理能力为10万m3/d.本文以该厂滤池为例介绍V型滤池主体的土建施工顺序,重点介绍后浇带、变形缝、V型槽、H型排水槽施工和施工缝处理以及滤板的制作与安装等问题.
The fourth water plant had been built since October 1996 in Zhuzhou city, the first phase of this project with capacity of l00 thousand cubic meters per day had been completed in December 1999. The procedure for construction of V-filter is introduced according to the filter of this plant. Construction of after-casting belt, transfigure crack, V-channel, H-drainage channel and treatment of construction crack, manufacture and installation of filter board are introduced emphatically.
关键词
V型滤池
V型槽
H型摊水槽
滤板
V-filter
after-casting transfigure crack
V-channel
H-drainage channel
filter board