摘要
简述工程中常用零序差动保护方法,以某电厂一台1000 MW机组的主变为试验对象,论述了一种利用区外单相接地短路进行极性校验的方法,通过对零序电流的记录与分析,所得结论验证了极性的正确性以及校验方法的有效性。
This paper briefly describes the zero sequence differential protection method commonly used in engineering. Taking the main transformer of a 1000 MW unit in a power plant as the test object, a method of polarity checking using out-of-zone single-phase grounding short circuit is discussed. Through recording and analyzing zero sequence current, the conclusion obtained verifies the correctness of polarity and the validity of the checking method.
作者
宋梦琼
SONG MENG QIONG(Technical Skills Training Department of Wuhan Electric Power Technical College, Wuhan, Hubei 430079)
出处
《武汉电力职业技术学院学报》
2018年第4期47-49,共3页
Journal of Wuhan Electric Power Technical College
关键词
零序差动保护
极性校验
单相接地短路
Zero sequence differential protection
Polarity check
Single-phase grounding short circuit