深基坑分层分段放坡开挖临时支撑架设滞后问题研究

Study on the Lag of Temporary Support in Layered and Segmented Excavation of Deep Foundation Pit
原文传递
导出
摘要 以武汉地铁阳逻线的车站基坑工程为背景,应用FLAC3D数值计算软件对基坑分层开挖与逐级架撑过程进行模拟分析。通过对比几种支撑架设滞后方案的计算结果,总结了开挖面支撑架设滞后时,围护结构变形及钢支撑轴力的变化特征。结果表明:滞后支撑的数量相同的情况下,开挖面横排钢支撑架设滞后对基坑受力变形的影响最小,纵列钢支撑架设滞后影响最大;通过调整已架设钢支撑的轴力来控制缺撑区域的变形是可行的。 Based on the excavation of an underground metro station in YangLuo line of Wuhan Metro,this paper employs the numerical analysis software FLAC3 D to simulate the complex staged excavation process.By comparing the results,the research draws a general conclusion about the deformation characteristics of retaining structure and the change of pre-stress on steel support.The analysis results indicate that:the lack of horizontal steel support has the least influence while the lack of vertical steel support is the worse with the same lack of steel support.Despite its limited effectiveness,but the numerical simulation also show that,it is feasible to control the deformation of the retaining structure by adjusting the pre-stress on completed steel support.
作者 吴穷 范小春 李洁 WU Qiong;FAN Xiao-chun;LI Jie(School of Civil Engineering and Architecture,Wuhan University of Technology,Wuhan 430070,China)
出处 《武汉理工大学学报》 CAS 北大核心 2018年第6期70-75,共6页 Journal of Wuhan University of Technology
关键词 深基坑 有限差分法 钢支撑 预加轴力 deep foundation pit finite difference method steel support pre-stress
  • 相关文献

参考文献6

二级参考文献48

共引文献153

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部