大志山注浆帷幕防治水工程大型抽水试验 被引量:5

Steady-flow pumping test of groundwater blockage by grouting curtain in Dazhishan mine
下载PDF
导出
摘要 矿山帷幕注浆防治水工程具有典型隐蔽工程的特点,其施工质量检查鉴定和堵水效果评价一直没有可依照和遵循的标准,现有的单因素评价或多因素混合评价都难以给出定量结论,大型抽水试验是目前最为直接且有效的方法,但因工程复杂费用昂贵,很少使用.本文基于Dupuit稳定井流基本原理,在充分调查、分析矿区生产现状、水文地质条件、帷幕勘察、设计、施工资料的基础之上,设计并成功实施一大型抽水试验,使用单井抽水多个观测孔计算公式求解注浆后复合岩体的等效渗透系数,采用拟"大井法"对矿井深部的涌水量进行预测,其成果直接用于大志山帷幕注浆工程的质量检测与评价鉴定,取得较为满意的效果. The grouting curtain, with the typical characteristics of underground engineering, has no specific standard to inspect its construction quality and evaluate the effect of grouting, and the quantitative conclusion is difficult to be given by single factor or multiple factors combination, so the large pumping test, which is rarely be implemented in practice because of its expensive and complicated characteristics,could be the most direct and effective method. Based on the basic principle of Dupuit's steady well flow, a large pumping test was designed and completed after the sufficient investigation and analysis of production status, hydrogeological conditions and grouting curtain document of investigation, design and construction about Dazhishan mine.In the test, the equivalent permeability coefficient of composite rock body after grouting curtain was solved by using single well pumping-multiple observation hole calculation formula, and the amount of water in deep was forecasted using 'virtual large diameter well' method, which was used in quality evaluation and appraisal in grouting curtain water plugging engineering in Dazhishan mine, and the results are satisfactory.
出处 《武汉工程大学学报》 CAS 2015年第8期6-12,共7页 Journal of Wuhan Institute of Technology
基金 大冶市大志山矿业有限司提供项目经费支持
关键词 岩溶矿床 地下水防治 帷幕注浆 稳定井流 抽水试验 Karst water-filled deposit groundwater blockage grouting curtain steady-flow pumping test
  • 相关文献

参考文献6

二级参考文献24

  • 1张东成,钱运生.井间测量技术及其应用现状[J].勘探地球物理进展,2004,27(6):402-406. 被引量:7
  • 2罗平平,何山,张玮,赵庆锋.岩体注浆理论研究现状及展望[J].山东科技大学学报(自然科学版),2005,24(1):46-48. 被引量:38
  • 3李清松,潘和平,赵卫平.井间电阻率层析成像技术进展[J].工程地球物理学报,2005,2(5):374-379. 被引量:11
  • 4Hvorslev M J. Time lag and soil permeability in ground-water observations [R]. Bulletin No. 36, Waterways Experiment Station, Engineer Research and Development Center. Vicksburg, Mississippi: the US Army Corps of Engineers, 1951:50.
  • 5Chapuis R P. Shape factors for permeability tests in boreholes and piezometers[J]. Ground Water, 1989, 27 (5) : 647 - 654.
  • 6Ratnam S, Soga K, Whittle R W. Revisiting Hvorslev's intake factors using the finite element method [ J ]. Geotechnique, 2001, 51(7) :641 - 645.
  • 7Mathias S A, Butler A P. An improvement on Hvorslev' s shape factors[J]. Geotechnique, 2006, 56(10): 705- 706.
  • 8陈雨荪,颜明志.抽水试验原理与参数测定[M].北京:水利电力出版社,1985:91-99.
  • 9Tuma J J,Walsh R A.工程数学手册[M].欧阳芳锐,张玉平,译.北京:科学出版社,2002:532.
  • 10华北有色工程勘察院.邯钢集团沙河市中关矿业有限公司中关铁矿帷幕注浆工程施工设计[Z].2008.

共引文献69

同被引文献87

引证文献5

二级引证文献66

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部