摘要
随着技术的不断革新,间冷塔的施工工艺也在不断的完善,体系也越来越成熟.脚手架搭设也成为了间冷塔施工的安全保证前提,基于Ansys的有限元分析,结合青海桥头项目工程,针对X柱在浇筑混凝土的过程中各项荷载产生的力对模板支撑的影响做了简单分析.
With the continuous innovation of technology,the construction technology of cooling tower is also constantly improving;the constraction system also has become more and more mature.The scaffolding erection has also become a premise for cooling tower construction security assurance.This article is based on Ansys finite element analysis,combined with Qinghai Qiantou project,to do simple analyses of forces under every load on template support when pouring concrete of X-column.