摘要 碾压砼在我国是最近几年发展起来的一种新兴筑坝技术.本文总结了在铜街子工程进行的连续上升至16m高度快速施工经验,高块连续浇筑须具备的施工条件,核算通仓浇筑带来的温度应力问题,为了解高块连续浇筑的坝体温度及变形,布置了监测仪器,并总结了观测成果。 RCC Placement is a new dam construction technology developed in China recently. These paper sums up the experince for rapid and continuous placement of RCC by 16m high carried out at Tongjiezi project ,and poses the construction conditions which meet the requirements of contiuous placement of high monolith. The temperature stress araised by placement from one abutment to other was calculated. The monitoring instruments were embedded to see the temperature and deformation in the dam section which was placed high without stop,The instrumentation result were analyzed.
机构地区 水电七局
出处 《四川水力发电》 1992年第A05期52-57,共6页 Sichuan Hydropower
基金 国家"七五"科技攻关17-02一06专题研究之一
关键词 碾压 筑坝 温度控制 施工 construction of RCC, temperature control, temperature computaion, temperature stress monitoring, placement of high monolith, delivery of concrete during placement.
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部