摘要
该文论述了北仑电厂二期工程3×600MW机组建设过程中,因国外设计技术失误引起的汽温偏低问题及处理方法,对锅炉设计制造、安装和调试有较大借鉴意义。
Beilun Power Plant, during its second construction stage of 3×600MW sets, encovntered the problem of depressed steam temperature, caused by some oversea technical design error. The paper presents a report together with ways of solving the problem, which may serve as a valuable reference for design, manufacutre, installation and commissioning of boilers.
出处
《发电设备》
2004年第1期30-33,共4页
Power Equipment