摘要
从多角度总结了役检试块的不同类型,并分别从试块涉及的相关单位、技术文件体系以及总清单等方面系统地介绍了M310堆型核电厂在役检试块采购实践情况。最后研究提出核电工程项目役检试块采购工作从ATP至FCD及后续的阶段式策划分析,为更好地满足工程现场装料及运行需求提供建议支持。
The service test block types are summarized from multi angles,and the M310 reactor nuclear power plant's procurement practice is systematically introduced respectively from the aspects of the lesl block related units,file system and the total list.At last,the service lesl block purchasing stage planning of nuclear power project is proposed from ATP lo FCD and follow-up,to belter meet the project site loading and operation requirements and lo provide recommendations for supporting.
出处
《陕西电力》
2016年第7期70-73,共4页
Shanxi Electric Power
基金
国家自然科学青年基金资助项目(51201064)
关键词
核电项目
役检试块
采购策划
采购实践
nuclear power project
service inspection test block
procurement planning
procurement practices