摘要
斜拉桥由索塔、主梁、斜拉索组成,其主塔施工是斜拉桥施工的重点和重要控制分项。文章介绍了拱门式主塔施工技术在针鱼岭大桥工程中的应用,分析了拱门式主塔设计的特点及技术优势,评述该技术可保证斜拉桥拱门式主塔施工的结构安全及施工速度。
The cable-stayed bridge is composed of cable tower,main beam,and stayed cable,the con-struction of its main tower is the focus and key control part for the construction of cable-stayed bridge.This article introduced the application of arch-type main tower construction technology in Zhenyuling Bridge engineering,analyzed the features and technical advantages of arch-type main tower design,and reviewed that this technology can ensure the structural safety and construction speed for arch-type main tower construction of cable-stayed bridges.
出处
《西部交通科技》
2014年第7期53-56,共4页
Western China Communications Science & Technology
关键词
斜拉桥
针鱼岭大桥
拱门式主塔
施工技术
Cable-stayed bridge
Zhenyuling Bridge
Arch-type main tower
Construction technology