摘要
文章结合大藤峡水利枢纽库区码头建设工程实例,根据该项目建设进度以及建设前后水位变化的情况,探讨适合该项目可行性研究阶段的码头建设方案,提出了"二级平台码头结构"与"高桩梁板直立式码头结构"两个建设方案,并通过优缺对比分析,选定"二级平台码头结构方案"为推荐方案,为同类型或类似情况的港口建设方案设计提供借鉴。
Combined with practical wharf construction project of Datengxia Hydraulic Complex reservoir area,and according to the construction progress of this project as well as the water level changes before and after the construction,this article discussed the wharf construction program of this project at feasibility study stage,proposed two construction programs of'two-level platform wharf structure'and'high-pile vertical slab wharf structure',and through the comparative analysis of advantages and disadvantages,it selected'two-level platform wharf structure program'as the recommended program,thereby providing the reference for port construction program design of the same type or under similar situations.
出处
《西部交通科技》
2015年第4期93-96,共4页
Western China Communications Science & Technology
关键词
码头
大藤峡水利枢纽
二级平台结构
高桩梁板直立式码头结构
建设方案
比选
Dock
Datengxia Hydraulic Complex
Two-level platform structure
High-pile vertical slab wharf structure
Construction programs
Comparison and selection