摘要
根据项目风险分析过程和富锦风力发电项目,阐述了风力发电项目风险因素的识别与评估方法,对不同的风险因素采取相应的应对策略和监控措施,并对项目外资贷款中的单一风险因素进行了定量分析。
Following the risk analysis process and taking the Fujin wind power project as an example, the risk factors involved with wind power projects are identified and analyzed, countermeasures and monitoring means are then suggested as appropriate for different risk factors, and a quantitative analysis is run for single risk factors of foreign loans.
出处
《黑龙江电力》
CAS
2003年第6期415-417,共3页
Heilongjiang Electric Power
关键词
风力发电
风险
分析
wind power generation
risk
analysis