结合上海某商务区区域能源项目,基于燃气冷热电三联供系统基本运行策略,计算了能源站用电负荷,并根据用电负荷计算结果,探讨了变压器配置和主接线形式,以合理规划设备投资,降低运行费用。
Combining by a business district regional energy project in Shanghai,based on the basic operation strategy of gas heating,cooling and electricity trigeneration system,the loads of power station were calculated.According to the calculation results,the transformer configuration and main wiring were discussed.It can reasonably plan the equipment investments and reduce the operation costs.
作者
景卉
JING Hui(East China Architectural Design&Research Institute,Shanghai 200002,China)
出处
《现代建筑电气》
2019年第4期23-26,共4页
Modern Architecture Electric
关键词
分布式能源站
燃气冷热电三联供
负荷计算
主接线形式
distributed energy station
gas heating,cooling and electricity trigeneration
load calculation
main connection mode