文章通过对既有隧道衬砌结构拆除作业工程案例进行分析表明,既有隧道衬砌结构拆除作业的风险不同于新建隧道工程风险,在该类风险与安全隐患分析的基础上从设计与施工角度提出了相应的控制措施,并依托山西杜公岭隧道病害处治工程应用实例,应用效果表明,充分的施工准备、合理的拆除方案、科学的拆除方式可以有效地管理与控制既有隧道衬砌结构拆除作业中的潜在风险,保障隧道施工安全。
Through the case analysis on demolition work of the existing tunnel lining structure,it shows that the risk of the demolition work of the existing tunnel lining structure is different from the risk of the new tunnel project.On the basis of the analysis,the corresponding control measures are put forward from the view of the design and construction.These control measures have been applied in the lining defect treatment project of the Dugongling tunnel in Shanxi.The application case shows that through the sufficient construction preparation,the reasonable demolition scheme and the scientific demolition type,the potential risks in the demolition of existing tunnel lining structures are controlled,ensuring the safety of tunnel construction.
作者
吴建军
许崇帮
杨槐
WU Jianjun;XU Chongbang;YANG Huai(The 5th Engineering Ltd. of the China Railway 11th Engineering Bureau Group Co. , Chongqing 400037;Bridge and Tunnel Research Center,Research Institute of Highway Ministry Transport,Beijing 100088)
出处
《现代隧道技术》
EI
CSCD
北大核心
2018年第A02期882-886,共5页
Modern Tunnelling Technology
基金
山西省交通科技项目(2017-1-6)
中铁十一局集团科技项目.
关键词
隧道工程
风险
衬砌结构
拆除
Tunnel engineering
Risk
Lining structure
Demolition