摘要
分析了广州发电厂员村热电厂制粉系统电耗偏高的原因,通过对制粉系统的一系列改进,使得制粉电耗由原来的27~30kwh/t降低至22~24kwh/t。降低了制粉电耗,提高了制粉系统运行的经济性。
The Guangzhou power plant Yuancun heat and power station put in production , the electric cost of the milling system is comparatively high are analyszed. through coal pulverizing are improved reduce milling electric cost, make milling electric cost from 27~30kwh/t to 22~24kwh/t and lift the boiler operation economy.