摘要
针对热态精炼渣能量利用问题,对原工艺进行改进,将废杂铜冶炼过程中产生的精炼渣在熔融状态下直接加入顶吹转炉进行处理,不仅节能降耗,而且缩短了作业周期,增加了产能,经济效益显著。
Aiming at energy utilization of refining flux slag,the original process was improved.The refining flux slag produced in scrap copper smelting process was filled to top-blown converter directly.This improvement gave an ideal result of saving energy,shortening the operating cycle,increasing productivity,and economic benefit was significant.
出处
《中国有色冶金》
CAS
北大核心
2015年第6期8-10,共3页
China Nonferrous Metallurgy
关键词
废杂铜冶炼
热态
精炼渣
顶吹转炉
能量利用
节能降耗
scrap copper smelting
flux
refining slag
top-blown converter
energy utilization
saving energy and reducing consumption