摘要
根据某厂房地面不均匀沉降、局部开裂现象 ,分析其产生的原因主要由于附近建筑工地人工挖孔桩施工 ,大量抽取地下水所致。并采用静压预制桩进行加固 ,控制沉降 ,处理效果明显。
The phenomenon of unequal subsidence and local cracking in a factory building is caused by mining of much groundwater from the manual excavated piles in a building ground nearby The static premoulded pile is adopted to strengthen ground base and control subsidence
出处
《安徽建筑工业学院学报(自然科学版)》
2003年第4期46-48,52,共4页
Journal of Anhui Institute of Architecture(Natural Science)
关键词
厂房
地面沉降
开裂
地下水
静压预制桩
unequal subsidence
crack
groundwater
static premoulded pile