期刊文献+

三峡二期下游围堰砼防渗墙复杂结构拆除爆破设计 被引量:2

Design of demolition blasting of complicated structure of concrete cut-off wall in second-stage downstream cofferdam of Three Gorges Project
下载PDF
导出
摘要 三峡二期下游围堰拆除工程砼防渗墙部分墙段内有灌浆施工时预埋的灌浆钢管及固定钢管的保持架,这种结构在以往的围堰防渗墙爆破拆除工程中没有先例。工程进度要求2002年7月1日前完成爆破设计和爆破试验及现场所有准备工作,7月1日进行防渗墙拆除爆破,确保一次爆破成功。介绍了在总结以往经验基础上应用现场爆破试验成果所进行的砼防渗墙拆除爆破设计和爆破效果分析。 With a limited demolition duration and a great quantity of excavation under water, especially the fact that there were grouting steel tubes and holding frames within the concrete cut-off wall, the work of the demolition of structure was of great challenge. The blasting design, site tests and all locale preparatory work were demanded to be completed before July 1,2002 according to the given schedule, and the demolition of the cut-off wall was scheduled to be carried out on July 1 and must be successful. The design of the demolition blasting of the concrete cut-off wall that was based on other project's experience and the site testing is introduced in this paper, the analysis of the blasting effect is also presented.
出处 《长江科学院院报》 CSCD 北大核心 2003年第B12期66-68,共3页 Journal of Changjiang River Scientific Research Institute
关键词 三峡工程 砼防渗墙 拆除 爆破设计 围堰 灌浆施工 demolition of the concrete cut-off wall blasting design charge spacing
  • 相关文献

参考文献2

  • 1GB6722-86.爆破安全规程[S].[S].,..
  • 2曹稼良.葛洲坝大江上游围堰砼防渗心墙拆除爆破技术[R].武汉:长江水利委员会,1988.

共引文献34

同被引文献5

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部