摘要
泉港老闸钢筋混凝土结构拆除工况复杂,根据具体情况分析了其安全影响因素,并介绍了现场控制措施。实践证明,所采用的现场控制措施是合适的,保证了爆区周围重要建(构)筑物的安全。
The environment of the old reinforced concrete floodgate needed to be demolished was complicated. The factors influencing the safety of the blasting were analyzed and the control measures on the spot were introduced. The practice showed that measure taken was effective, and the safety of the surrounding important structures was ensured.
出处
《长江科学院院报》
CSCD
北大核心
2003年第B12期69-71,75,共4页
Journal of Changjiang River Scientific Research Institute