摘要
可靠的电厂供水水源对火电厂的经济运行至关重要,特别在水资源日益紧缺地区,合理、客观地论证地区水资源及电厂供水情况关系到电厂规模甚至成立与否。本文针对某一电厂初期工程存在的设计枯水流量问题,提出了较为合理的解决方法,客观评价了电厂枯季供水问题,不但提高了工程质量,同时节约了大量工程投资。
The reliability of water supply resources is very important to the economic operation of the Thermal Power Station,especially in some areas which is in short of water resources increasingly,the reasonable and objective evaluation of the regional water resources and the condition of water supply to is relate to the Power Station construction scale even the establishment or not.In this paper some reasonable methods are put forward on the problem of design low-flow discharge in the feasibility phase of the project,which evaluated the problem of the water supply objectively during the dry season for the Power Station,increased project quantity and economized a large lot of project investment.
出处
《电力勘测设计》
2003年第4期39-42,共4页
Electric Power Survey & Design
关键词
电厂
供水水源
设计
枯水流量
low-flow gauging
statistics and analysis
actual collecting area
design discharge.