发电厂内厂用电并联切换方式的分析计算 被引量:1

ANALYSIS AND CALCULATION OF AUXILIARY POWER SWITCHING WITH PARALLEL CONNECTION IN POWER PLANT
下载PDF
导出
摘要 发变组单元接线,厂用变压器引自发电机端的发电厂,实现厂用电并联切换方式,可以简化运行操作,保障辅助设备的连续供电和运行操作安全。文中分析了变压器变比误差、短路阻抗对并联切换的影响,计算了满足并联切换条件时机组间的允许负荷差异。 In order to simplify operation and ensure continuous power supply for auxiliary equipment and safe operation, a power plant where a generator and a main transformer are joined into a unit, and the transformers for plant power supply are linked to generators, can implement power supply in parallel operation. This paper analyzes the influence of the error of the transformer normal tapping ratio, short-circuit resistance and the load of plant power supply on parallel operation, and calculates the difference between the allowable loads for different units while parallel operation conditions are satisfied.
作者 王世界
机构地区 二滩水电厂
出处 《水电自动化与大坝监测》 2004年第1期25-28,共4页 HYDROPOWER AUTOMATION AND DAM MONITORING
关键词 发电厂 厂用电 并联切换 power plant plant power supply parallel operation
  • 相关文献

参考文献2

共引文献5

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部