核电厂调试工期的优化方案 被引量:1

Optimization of the Commissioning Period of Nuclear Power Plant
下载PDF
导出
摘要 目前,国内核电建设受设备产能和建设经验等因素影响,调试工作往往不能如期开展,可能导致总工期拖延。合理规划调试工期和逻辑,根据实际情况对调试工期进行优化,是消减部分工期拖延的有效手段之一。文章通过研究百万千瓦级核电机组建设时遇到的常规情况,在以往参加核电机组调试工期优化实践的基础上,分析和探讨了调试计划制订特点、计划执行中的困难和调试工期优化的对策,提出从项目全局的角度实施动态调整优化的方案,将向调试本身要时间、向接口要时间、向管理要时间三条途径相结合,论述了活动工期压缩和调试逻辑调整、调试内外部接口优化以及管理方式优化的具体方法和重点举措,对调试工期优化的效果和方向、提高工程管理能力和控制优化原则进行了总结。 Due to current equipment manufacture capacity, construction experience and other factors, commissioning of nuclear power projects was used to be postponed, which could lead to delay of the whole project. Based on the actual situation, optimization of commissioning period and its logic could be an effective way to improve this situation to some extent. Based on previous practice and experience in the schedule management for the commissioning nuclear power projects, this paper analyzes and discusses the characteristics of make commissioning plan and the difficulties of program implementation and strategies of commissioning plan optimization, discusses and presents ways of dynamic plan adjustment and optimization at the vision of entire project, synthesizes the methods of time management through commissioning itself, interface and management, expounds measures for the timing and optimization of commissioning schedule and commissioning period, and sums up the ways of optimization of commissioning period, improving management capabilities and control of optimization principles.
出处 《中国核电》 2014年第2期128-133,共6页 China Nuclear Power
关键词 核电 调试 计划 进度优化 nuclear power commissioning planning schedule optimization
  • 相关文献

参考文献5

二级参考文献6

  • 1KERZNERHAROLD.项目管理计划进度和控制的系统方法[M].杨爱华,等译.北京:电子工业出版社,2002:248-271,249-273.
  • 2高德拉特.关键链:突破项目管理的瓶颈[M].北京:电子工业出版社,2006:92-100.
  • 3FARUK GUL, WOLFGANG PESENDORFER. Self - control, revealed preference and consumption choice [ J]. Review of Economic Dynamics, 2004 (7) : 243 - 264.
  • 4LAIBSON DAVID. Golden Eggs and Hyperbolic Discounting [ J ]. Quarterly Journal of Economies, 1997, 12 (2) : 443 -478.
  • 5O 'DONOGHUE TED, RABIN MATI'HEW. Doing it now or later [J]. American Economic Review, 1999, 89 (1): 103 - 124.
  • 6James P Lewis.项目计划、进度与控制[M].北京:清华大学出版社,2002.

共引文献18

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部