摘要
针对航天试验项目管理中存在的多模式资源受限项目调度问题,首先通过建立数学模型进行了描述;然后基于CPLEX软件平台设计了求解流程,并采用优化编程语言予以实现;最后通过实例分析验证了求解方法的有效性,并将结果制成甘特图,展现了整个项目的活动时间安排和资源消耗情况,为航天试验人员进行项目管理和决策提供可靠依据。
Aiming at the multi-mode resource-constrained project scheduling problem in aerospace test project management,a mathematical model is firstly established to give a description.Then,based on CPLEX software,a computation flow is presented and implemented by optimized programming language. Finally,the effectiveness of computation flow is validated through analysis of examples and computation re-sults are made into the Gantt chart to show the project schedule and resource consumption clearly,which provides a reliable basis for project management and decision-making for aerospace testing personnel.
出处
《装甲兵工程学院学报》
2015年第5期89-93,共5页
Journal of Academy of Armored Force Engineering
基金
军队科研计划项目
关键词
航天试验
项目管理
资源受限项目调度
aerospace test
project management
resource-constrained project scheduling