广州石化动力事业部三台220t/h煤粉炉六台钢球磨煤机噪声治理工程采用隔声墙加吸声板的处理方法,使磨煤机室外噪声明显下降。
This article specifies the noise control of steel-ball coal mill in 220t/h coal-burned boiler of Power Station of Guangzhou Petrochemical Complex.Sound insulation and absorption are adopted in this project.Sound obviously drop in outside of coal mill compartment.
出处
《噪声与振动控制》
CSCD
2004年第1期42-44,共3页
Noise and Vibration Control