摘要
网络图的结点拼接绘制法的基本作法是:首先找全网络结点并弄清每个结点的状况,然后找出拼接中心,绘制成拼接网络图,最后将拼接图转换为原始网络图。它适用于较复杂的原始网络图的绘制。
The drawing method of the construction in a network diagram has been developed on the basics of comfining the users practical skills with the theory of the arrowed-line network diagram. Its fundamental process is find out all the joining points in the network, check up the condition of every joining point,try to discover the center of the construction,draw up the final networck diagram and then turn this figure into a fasic diagram. This method is applicable to draw more complicate fasic network system.
出处
《烟台大学学报(自然科学与工程版)》
CAS
1992年第3期83-90,共8页
Journal of Yantai University(Natural Science and Engineering Edition)
关键词
变动前结点
网络图
结点拼接绘制
Net work diagram. Dissimilar drawing up joining point. Changing front joining point. Parallel arrowed-line joining point.