摘要  以10座地泵房、882根碎石桩挤密软土地基处理为例,总结振冲置换法处理我国西部软土地基的具体施工工艺和施工质量控制。从效益上分析,经这种方法处理后的软粘土地基,承载力提高了3倍。在设计要求承载力不超过200kPa的地基结构,采用振冲置换法比较经济。与预制混凝土桩基础相比,可节省工程费用60%左右。这种技术在经济欠发达的西北部地区极有推广应用价值。 The specific process and operational quality control for soft soil base treatment in west China are summarized on the basis of operation of 882 piles in the 10 pump rooms. The application on the base is rare both at home and abroad and it is worthy introducing here. Compared to the prefabricated cement pile about 60% engineering expenditure is saved and bearing capacity of the treated basement raises by 3 times. Therefore it should be popularied in the undeveloped economic area, such as the west China.
作者 吴丽萍
出处 《地质找矿论丛》 CAS CSCD 2004年第1期67-70,共4页 Contributions to Geology and Mineral Resources Research
关键词 地基 振冲法 施工 base vibration-percussive technology operation
  • 相关文献

参考文献4

  • 1张捷 叶书麟.地基处理工程实例应用手册[M].北京:中国建筑工业出版社,1988..
  • 2盛崇文.地基处理手册(第二舨)[M].北京:中国建筑工业出版社,2000..
  • 3张捷 叶书麟.地基处理工程实例应用手册[M].北京:中国建筑工业出版社,1988..
  • 4盛崇文.地基处理手册(第二版)[M].北京:中国建筑工业出版社,2000..

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部