简要介绍N125-13.24/535/535-Ⅱ型汽轮机在梅县发电厂#3、#4机组工程的安装、调试过程中防止转子弯曲而采取的一些措施,分析调速保安系统出现故障的原因及其处理经验。
For installing and debugging the steam-turbine unit No.3 and No.4 of N125-13.24/535/535-Ⅱ in Meixian Power Plant,some measure to prevent the flexure of rotor had been adopted and what cause the faults of speed control and protection system are analyzed.
出处
《江西电力职业技术学院学报》
CAS
2004年第2期15-17,共3页
Journal of Jiangxi Vocational and Technical College of Electricity