乌鞘岭特长隧道方案设计 被引量:28

Tentative project of Wushaoling tunnel
下载PDF
导出
摘要 乌鞘岭隧道为目前我国最长的铁路隧道 ,长 2 0 .0 5km ,其地质条件复杂、工期极其紧张、工程规模巨大 ,引起了国内外地下工程界的瞩目。文章通过越岭隧道限坡、长度、单双洞方案比选介绍了乌鞘岭特长隧道方案选择情况 ;并从隧道施工方案、防排水、运营和施工通风等方面较为系统地介绍了隧道的设计概况。 Wushaoling tunnel, the longest tunnel in China at present with a length of 20050m , attracts the attention in the field of underground works due to its complex geological condition, strict time limit of construction and tremendous engineering work. This paper introduces the selection of the tentative projects of this watershed tunnel in the respect of limit slope, tunnel length and the comparison between a double-track tunnel or twin single track tunnels and gives a general introduction to the design of this extra-long tunnel in regard to construction plan,waterproofing and drainage, operation and construction ventilation.
出处 《现代隧道技术》 EI 2004年第2期1-7,共7页 Modern Tunnelling Technology
关键词 乌鞘岭隧道 方案设计 辅助坑道 Wushaoling tunnel Tentative design Access drifts
  • 相关文献

同被引文献683

引证文献28

二级引证文献887

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部