摘要
结合郑州市郑东新区某工程实例,在满足力学计算和现行规范的前提下,对基础方案进行比较,确定采用600灌注桩是一个经济、可靠的地基处理方案,对今后该地区类似工程基础方案的确定,起一定的参考作用。
In this paper, on the premise of sufficing for the calculation of mechanics and the current criterion, it is combined with an example of civil engineering by comparing different base projects, which is in ZhengDong New Zone, site-cased RC pile diameter 600 to confirm an economic and credible project that deals with the groundsite. To the analogous civil engineering of this area, it has some referenced effect on the confirmation of base scheme in the future.
出处
《平顶山工学院学报》
CAS
2004年第1期45-47,共3页
Journal of Pingdingshan Institute of Technology
关键词
高层建筑
基础选型
CFG桩复合地基
桩基
disposal of groundsite
base scheme
comparison of economy
CFG stake compound base