摘要
针对柳林电厂空气预热器积灰严重的问题,采用弱爆炸波清灰技术对原有吹灰系统进行改造取得良好效果,并用数据对比进行了分析说明。
The problem of serious ash of air reheater at Liulin power plant is reviewed. The principle of reforming the soot blow system of air reheater to use weak explosion wave technique to clear ash is raised. The excellent result is acquired. Some data are compared and analyzed.
出处
《山西电力》
2004年第2期53-55,共3页
Shanxi Electric Power