三峡首批机组并网调试中三万线高抗保护误动作分析 被引量:1

ANALYSIS ON MALOPERATION OF PROTECTIVE RELAYING FOR HIGH VOLTAGE REACTOR IN SANXIA-WANXIAN TRANSMISSION LINE DURING COMMISSIONING TEST FOR INTERCONNECTING FIRST BATCH OF GENERATING SETS IN THREE GORGES LEFT BANK HYDROPOWER PLANT WITH POWER GRID
下载PDF
导出
摘要 文章对三峡首批机组并网调试中出现的三万线高抗保护误动作进行了深入分析,排除了高抗内部发生故障的可能性,得出了高抗低端的电流互感器(CT)极性接反导致高抗保护动作的结论。由于准确及时排除了错误,使调试得以顺利进行。 During the commissioning test for interconnecting the first batch of generating sets in Three Gorges left bank hydropower plant with power grid the maloperation of the protective relaying for high voltage reactor in Sanxia-Wanxian transmission line occurs. After analyzing the maloperatoin in-depth the possibility that the inside fault of the reactor occurs is ruled out and the reason causing the maloperation is found, i.e., the polarity of the CT at the low side of high voltage reactor is connected in reverse. After the defect is removed in time, so that the commissioning test can successfully proceed.
出处 《电网技术》 EI CSCD 北大核心 2004年第10期9-12,共4页 Power System Technology
关键词 电力系统 高抗保护 零序电流 差动保护 极性 并网调试 机组 继电保护 三峡工程 Electric equipment protection Electric lines Electric potential Electric power system interconnection Electric reactors HVDC power transmission Hydroelectric generators Standby power systems
  • 相关文献

参考文献3

  • 1国家电力调度通信中心.三峡首批机组并网调试调度实施方案(第一阶段)[Z].北京:国家电力调度通信中心,2003..
  • 2长江水利委员会长江勘测规划设计研究院.左一电站线路及电抗器保护接口原理图[Z].武汉:长江水利委员会长江勘测规划设计研究院,2003..
  • 3国电南京自动化股份有限公司.WDK-600微机型电抗器保护柜电气原理图[Z].南京:国电南京自动化股份有限公司,2003..