模糊层次分析法在Duber Khwar项目风险评价和投标决策中的应用研究 被引量:31

Study on application of Fuzzy-AHP in risk evaluation and bidding decision-making of Duber Khwar hydropower project
下载PDF
导出
摘要 本文提出了以层次分析法和模糊数学为基础的国际工程投标风险评价与决策的模型 ,包括 :国际工程投标风险的辨识、风险评价及投标决策的过程。结合巴基斯坦DuberKhwar水电工程项目的投标实例 ,确定了模型中的参数并进行了分析计算 ,结果合理。通过此模型能为决策者提供有力的支持 ,从而为正确的投标决策提供定量依据。 The model of risk assessment and decision-making for international project bidding based on AHP and fuzzy mathematics is pressented in this paper, including the process of risk identifcation of international project bidding, risk analysis and decision-making for bidding.With the example of duber Khwar hydropower project bidding, parameters in the model were established amd analysis and calculation were carried out.The conclusion is proved to be reasonable. Such model supplies the convincing supports to the decision maker, and as a result, supplies the quantitative basis for successful bidding decision-making.
作者 彭锟 强茂山
出处 《水力发电学报》 EI CSCD 北大核心 2004年第3期44-50,共7页 Journal of Hydroelectric Engineering
关键词 层次分析法 模糊数学 国际工程 风险管理 工程投标 AHP fuzzy international project risk management project bidding
  • 相关文献

参考文献6

  • 1Gates. M. Bidding Strategies and Probabilities[ A ]. Construction Division. ASCE, 1967.
  • 2Cooper, Dale F. Risk analysis for Large Project:Models, Methods and Cases[ J]. John Wiley & Sons Ltd, 1987.
  • 3Orlovsky S.A. Decision-making With a Fuzzy Preference Relation[ J]. Fuzzy Sets and Systems, Vol. 1, No.3,1978.
  • 4Gadsdon J. Chapman C. B. Risk analysis as a control feature in project management [ A ]. Transactions of the 7th International Cost Engineering Congress[ C]. London: 1982, C3 - 1 - C3 - 11
  • 5Larry G. Crowley, Member, ASCE, and Domm E. Haneher, Fellow, ASCE. Risk Assessment of competitive procurement[J]. the Journal of Construction Engineering and Management, June, 1995.
  • 6杨赞锋,赵彪.水电工程承包商的风险及防范策略[J].人民长江,1998,29(9):14-15. 被引量:3

共引文献2

同被引文献268

引证文献31

二级引证文献242

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部