摘要
介绍了桩板式挡土墙在宝兰铁路二线的施工情况 ,从施工工艺、既有线防护、混凝土灌注等方面进行了论述 ,指出该施工方法快捷可行 。
The construction situations of pile plank retaining wall in Baolan second railway line are introduced and discussed from construction technology, concrete pouring, railway line protection and other aspects. Practice shows this construction method is convenient and practicable, which ensure the normal service of the railway.
出处
《山西建筑》
2004年第13期59-60,共2页
Shanxi Architecture
关键词
既有线
桩板式挡土墙
施工
haven-built railway line, pile-plank retaining wall, construction