摘要
针对S201线克拉玛依至榆树沟段公路改建工程沿线部分路段地下水位较高,清表后无法进行填前碾压,故采用风积沙进行换填,从而达到清表压实问题及风积沙降低工程造价。
Becanse the higher lenel of underground weter in the highway section from szol line to Kelamayi in reconstruction the
project line and after the highway section is cleaned, we cannot ron before filling out, so the method of aeolian accumulation sand must
be used to deal with cleaning the surface and reducing the project cost.
出处
《辽宁省交通高等专科学校学报》
2004年第2期33-34,共2页
Journal of Liaoning Provincial College of Communications
关键词
公路工程
公路改建
风积沙
换填
软弱地基
处理
Aeolian Accumulation sand
Change and fill out
Soft foundation
treatmeat