摘要 为了完成某公司的智能制造转型计划,对该公司车间的生产流程、生产布局以及产品的生产工艺进行了调研,根据该车间的生产特点,将其归类为混合流水线车间调度(HFSP)这一典型的NP-hard问题。以最短作业时间(SPT)调度为优化目标,使用遗传算法去解决这一问题。具体方法上使用Plant Sim-ulation仿真软件,结合现场生产实际情况,搭建起车间流水线生产模型,应用遗传算法实现最优排序,得到近似最优解。经过遗传算法计算后的生产作业序列,理论上按此指导进行生产,总的作业时间可以缩短15%左右,从而提高企业生产效率;另外,厂家只需要导入即将执行的产品数量及工艺信息到模型,经过模型计算即可获得推荐排序。因此,此方式具有一定的实际应用价值和指导意义。 In order to complete the intelligent manufacturing transformation plan of a company, the production process, production layout and product production process of the company’s workshop were investigated. According to the production characteristics of the workshop, it was classified as a typ-ical NP-hard problem of hybrid flow shop scheduling (HFSP). The shortest operation time (SPT) scheduling is taken as the optimization goal, and genetic algorithm is used to solve this problem. In the specific method, Plant Simulation software was used to build the production model of the workshop assembly line combined with the actual situation of the field production, and the genetic algorithm was used to achieve the optimal sequencing, and the approximate optimal solution was obtained. After the genetic algorithm calculation of the production sequence, theoretically according to this guidance for production, the total operation time can be shortened by about 15%, so as to improve the production efficiency of enterprises;In addition, the manufacturer only needs to import the product quantity and process information to be executed into the model, and the recommended ranking can be obtained after the model calculation. Therefore, this method has certain practical application value and guiding significance.
作者 姚艳祥
出处 《计算机科学与应用》 2024年第2期268-276,共9页 Computer Science and Application
  • 相关文献

参考文献5

二级参考文献36

  • 1曹振新,朱云龙.混流轿车总装配线上物料配送的研究与实践[J].计算机集成制造系统,2006,12(2):285-291. 被引量:29
  • 2尚文利,史海波,邱文萍,何柏涛.基于RFID的混流装配汽车生产线物料动态配送研究[J].机械设计与制造,2007(2):157-159. 被引量:21
  • 3宋华明,马士华.混合装配流水线上最小makespan的协同优化[J].系统工程理论与实践,2007,27(2):153-160. 被引量:11
  • 4B. Rekiek, Pierre De Lit, and A. Delchambre. Designing mixed-product assembly lines [J ] . IEEE Transactions and Au- tomation, 2000, 16 (3): 268-280.
  • 5BEHNAMIAN J,GHOMI S F M T,ZANDIEH M.A multi-phase cov-ering Pareto-optimal front method to multi-objective scheduling in arealistic hybrid flow-shop using a hybrid meta-heuristic. ExpertSystems with Applications . 2009
  • 6FENG Ming-yue,TANG Shao-xun,LI Huaet al.Orthogonal particleswarm optimization for multi-objective Job-Shop scheduling problems. Proc of the 2nd International Conference on Computational In-telligence and Natural Computing . 2010
  • 7Ruiz,Ruben.The hybrid flowshop scheduling problem. European Journal of Operational Research . 2010
  • 8Erwin Pesch,Malgorzata Sterna.Late work minimization in flow shops by a genetic algorithm. Computers and Industrial Engineering . 2009
  • 9Betul Yagmahan,Mehmet Mutlu Yenisey.A Multi-objective Ant Colony System Algorithm for Flow Shop Scheduling Problem. Expert Systems With Applications . 2010
  • 10Framinan J,Leisten R.A heuristic for scheduling a permutation flowshop with makespan objective subject to maximum tardiness. International Journal of Production Economics . 2006

共引文献31

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部