为响应国务院《深化收费公路制度改革取消高速公路省界收费站实施方案》,实现不停车快捷收费,开展广佛高速公路取消省界收费站工程建设。该工程中ETC门架系统的完成度直接影响整个任务的完成情况,本文从ETC门架系统布设方法和原则、施工流程等方面介绍,为取消高速公路省界收费站同类型施工提供参考和借鉴。
In response to the State Council’s “Deepening the reform of the toll road system to cancel the implementation plan of highway provincial boundary toll stations”, and to realize fast tolls without parking, the construction of the provincial boundary toll station cancelled by Guangfo Expressway was carried out. The completion of ETC door frame system in this project directly affects the completion of the whole task, and this paper introduces the method and principle of ETC door frame system laying, construction process, etc., providing reference for the cancellation of the same type of construction of the highway provincial boundary toll station.
出处
《土木工程》
2020年第8期781-786,共6页
Hans Journal of Civil Engineering