智能变电站配置文件管控系统建设

The Configuration File Management and Control System Construction of Smart Substation
下载PDF
导出
摘要 国内电网智能变电站的设计、调试、验收、运维等各阶段,均须依靠全站配置文件(SCD文件)开展相关工作。正是由于建设调试过度依赖系统集成商和设备厂家、配置文件版本管控粗放、扩建过程停电影响范围不可控、配置文件修改过程不易受控,对智能变电站安全运行留下了隐患。因此,依据相关国网标准对智能变电站二次系统进行有效管理和建设势在必行。 The design, commissioning, acceptance, operation and maintenance of the Smart Substation in China, rely on the total station configuration file (SCD file) to carry out related work. Because construction commissioning relies on system integrators, equipment manufacturers, uncontrolled configuration files version, uncontrolled blackout range during the expansion process and uncontrolled configuration file modification process, smart substation has hidden dangers. It is imperative to carry out effective management and construction of the secondary system according to the relevant state grid standards.
出处 《智能电网(汉斯)》 2017年第5期307-312,共6页 Smart Grid
  • 相关文献

参考文献3

二级参考文献27

  • 1常弘,茹锋,薛钧义.IEC61850语义信息模型的实现[J].电网技术,2005,29(12):39-42. 被引量:23
  • 2Q/GDW 383-2009智能变电站技术导则[S].2009.
  • 3国家电网公司.Q/GDW383-2009智能变电站技术导则[S].北京:中国电力出版社,2009.
  • 4国家电网公司.Q/GDW396-2009IEC61850工程继电保护应用模型[S].北京:中国电力出版社,2010.
  • 5Q/GDW383--2009智能变电站技术导则[S].北京:中国电力出版社,2009.
  • 6徐成斌,孙一民.数字化变电站过程层GOOSE通信方案[J].电力系统自动化,2007,31(19):91-94. 被引量:125
  • 7国家电网公司.配网生产抢修指挥平台功能规范[S].2012.
  • 8IEC 61850-6 Edition 2.0 Communication networks and systems for power utility automation~ Part 6 configuration description language for communication in electrical substations related to IEDs[S]. 2009.
  • 9IEC 61850-7-3 Edition 2.0 Communication networks and systems for power utility automation~ Part 7-3 basic communication structure common data classes[S]. 2010.
  • 10孙一民,裘愉涛.智能变电站设计配置一体化系统:中国,102611199[P].201207-25.

共引文献105

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部