摘要
以北京地铁6号线8标盾构区间工程为例,对盾构法掘进施工的测量控制进行了系统阐述,详细介绍了盾构法掘进施工过程的平面控制网和高程控制网测量、联系测量、盾构机姿态测量和管片姿态测量等测量方法及工艺流程,为今后盾构法隧道施工控制测量工作积累了经验。
Taking the shield-driven tunnel works of Beijing Subway Line 6 Section 8 of as an example,the survey control of construction in shield tunneling was systematically elucidated in this paper,moreover the measure methods and technical process such as wire control measure in shield tunneling,connection survey inside and outside the tunnel,height measure-ment,the attitude detection of shield machine and duct piece were presented in detail,which would accumulate experiences in the field of survey control of construction in shield tunneling.
出处
《铁道建筑技术》
2016年第S1期237-240,共4页
Railway Construction Technology
关键词
盾构隧道
城市地铁
施工测量
姿态检测
shield tunneling
urban subway
construction survey
attitude detection