摘要
结合昆明轨道交通6号线二期工程菊华综合枢纽站地下连续墙工程,简要阐述超深地连墙成槽、钢筋笼吊装、接头处理措施、水下混凝土灌注等关键技术,这对昆明地区的超深地连墙施工具有一定指导意义。
Combined with the underground continuous wall construction of Juhua integrated hub station in the second phase of Kunming Metro Line 6,this paper gives a brief description of the super deep underground continuous wall reinforcement slots,steel cage hoisting,joints treatment measures and underwater concrete pouring and other key technologies,which has certain guiding significance for the super deep underground continuous wall construction in Kunming.
出处
《铁道建筑技术》
2016年第S1期351-354,共4页
Railway Construction Technology
关键词
地铁车站
地连墙
超深
subway station
ground continuous wall
super deep