Great progress was achieved in HIRFL-CSR project in the year of 2003. A large number of components has been completed, tested, installed, and commissioned, especially for the HIRFL-upgrade, for the new injection beam ...Great progress was achieved in HIRFL-CSR project in the year of 2003. A large number of components has been completed, tested, installed, and commissioned, especially for the HIRFL-upgrade, for the new injection beam line to the CSRm and for the CSRm. The project is now in the transition from the construction to the installation and commissioning phase. Component delivery and installation is proceeding in accordance with schedule. On the average more than 98% of the components have been contracted. More than 350 magnets have been manufactured. The magnets, the power supplies, the vacuum system and the beam detectors for the injection beam line to the CSRm have been installed. All the magnets for the CSRm have been展开更多
Construction and installation of HIRFL-CSR storage ring complex are nearing completion. The main task of HIRFL-CSR project in 2005 was the commissioning of the main ring CSRm. The first first-turn commissioning of CSR...Construction and installation of HIRFL-CSR storage ring complex are nearing completion. The main task of HIRFL-CSR project in 2005 was the commissioning of the main ring CSRm. The first first-turn commissioning of CSRm had been successfully done at the beginning of 2005, and then the attention was paid to get the stored beam in CSRm .展开更多
Considerable progress of HIRFL-CSR project was achieved in 2004. Up to now, about 98% of the total components have been completed, tested and installed. The injection beam line to CSRm has been commissioned by using d...Considerable progress of HIRFL-CSR project was achieved in 2004. Up to now, about 98% of the total components have been completed, tested and installed. The injection beam line to CSRm has been commissioned by using different ion species. The first first-turn commissioning of CSRm has been successfully done.展开更多
文摘Great progress was achieved in HIRFL-CSR project in the year of 2003. A large number of components has been completed, tested, installed, and commissioned, especially for the HIRFL-upgrade, for the new injection beam line to the CSRm and for the CSRm. The project is now in the transition from the construction to the installation and commissioning phase. Component delivery and installation is proceeding in accordance with schedule. On the average more than 98% of the components have been contracted. More than 350 magnets have been manufactured. The magnets, the power supplies, the vacuum system and the beam detectors for the injection beam line to the CSRm have been installed. All the magnets for the CSRm have been
文摘Construction and installation of HIRFL-CSR storage ring complex are nearing completion. The main task of HIRFL-CSR project in 2005 was the commissioning of the main ring CSRm. The first first-turn commissioning of CSRm had been successfully done at the beginning of 2005, and then the attention was paid to get the stored beam in CSRm .
文摘Considerable progress of HIRFL-CSR project was achieved in 2004. Up to now, about 98% of the total components have been completed, tested and installed. The injection beam line to CSRm has been commissioned by using different ion species. The first first-turn commissioning of CSRm has been successfully done.