To overcome the problems in design methodologies and construction control measures for the large open caisson, systematic research was conducted on the side friction calculation mode of the large open caisson. Based o...To overcome the problems in design methodologies and construction control measures for the large open caisson, systematic research was conducted on the side friction calculation mode of the large open caisson. Based on the field monitoring data of lateral soil pressure on the side wall of the open caisson for the southern anchorage of the Maanshan Yangtze River Highway Bridge, the statistical result of the side friction under different buried depths of the cutting edge of the open caisson was back-analyzed; and the side friction distribution of the large open caisson was underlined. The analysis results indicate that when the buried depth of the cutting edge is smaller than a certain depth H0, the side friction linearly increases with the increase in the buffed depth. However, as the buffed depth of the cutting edge is larger than H0, the side friction shows a distribution with small at both ends and large in the middle. The top of the distribution can be regarded as a linear curve, while the bottom as a hyperbolic curve. As the buffed depth of cutting edge increases continuously, the peak value of the side friction linearly increases and the location of the peak value gradually moves down. Based on the aforementioned conclusions, a revised calculation mode of the large open caisson is presented. Then, the calculated results are compared with the field monitoring data, which verifies the feasibility of the proposed revised calculation mode.展开更多
The complexity of geotechnical engineering and variability in construction circumstances of large extra caissons make the problem of maintaining appropriate sink attitude quite difficult, especially in keeping sink un...The complexity of geotechnical engineering and variability in construction circumstances of large extra caissons make the problem of maintaining appropriate sink attitude quite difficult, especially in keeping sink uniformity and achieving the expected final sink depth. A new construction control method is presented using ∞H theory, considering uncertainties in the mechanics model and external noise in the construction site parameters. The design method of an ∞H controller has consequently been obtained for large extra caissons. Control results using only constructor experiences are compared with simulation results using the ∞ H controller for a practical engineering situation, which indicates that the ∞H controller is successful in maintaining sink uniformity, avoiding sink as well as in achieving the expected final sink depth.展开更多
基金Project supported by China Communications Construction Company Limited(No.2008-ZJKJ-11)
文摘To overcome the problems in design methodologies and construction control measures for the large open caisson, systematic research was conducted on the side friction calculation mode of the large open caisson. Based on the field monitoring data of lateral soil pressure on the side wall of the open caisson for the southern anchorage of the Maanshan Yangtze River Highway Bridge, the statistical result of the side friction under different buried depths of the cutting edge of the open caisson was back-analyzed; and the side friction distribution of the large open caisson was underlined. The analysis results indicate that when the buried depth of the cutting edge is smaller than a certain depth H0, the side friction linearly increases with the increase in the buffed depth. However, as the buffed depth of the cutting edge is larger than H0, the side friction shows a distribution with small at both ends and large in the middle. The top of the distribution can be regarded as a linear curve, while the bottom as a hyperbolic curve. As the buffed depth of cutting edge increases continuously, the peak value of the side friction linearly increases and the location of the peak value gradually moves down. Based on the aforementioned conclusions, a revised calculation mode of the large open caisson is presented. Then, the calculated results are compared with the field monitoring data, which verifies the feasibility of the proposed revised calculation mode.
文摘The complexity of geotechnical engineering and variability in construction circumstances of large extra caissons make the problem of maintaining appropriate sink attitude quite difficult, especially in keeping sink uniformity and achieving the expected final sink depth. A new construction control method is presented using ∞H theory, considering uncertainties in the mechanics model and external noise in the construction site parameters. The design method of an ∞H controller has consequently been obtained for large extra caissons. Control results using only constructor experiences are compared with simulation results using the ∞ H controller for a practical engineering situation, which indicates that the ∞H controller is successful in maintaining sink uniformity, avoiding sink as well as in achieving the expected final sink depth.